l July 2020 -
August 2021:
Campaign
quiet phase
and public
phase
l August 2021-January
2022: Rowland Design to
refine schematic design to suit
fundraising potential
• Rowland Design to design
documentation, begin
construction documentation,
submit plans for permit review,
create bidding paperwork
l February
2022: Solicit
construction
bids/contractor
awarded
l March
2022: Finalize
delivery
contract
• Prepare for
demolition,
construction
and renovation
l May 2022:
Tentative
construction start
• Recommended
14-month
construction
timeline
l July 2022:
Punch list
l August
2023:
Renovation
complete,
members
move in
• Project
celebration
Fall 2023
l Fall 2023:
Home-
coming/
campaign
event