8
General Management
Dorm Wing Renovations
Common Area Renovations
Overlook Deck
Terrace and Entrance
Scope Contingency
Contingency
Soft Costs
Total Estimated $3,500,000
Construction Costs
Estimated Project Costs
l December 2019: House
Corporation hired CSL
Management, professional
Greek housing management
and consulting group, to assist
in the management of capital
improvement and build schedule
l December
2019-January 2020:
House Corporation
reviewed request for
proposal submittals,
interviewed and
awarded contract to
Rowland Design
l February 2020:
Engaged Pennington
& Company to
complete fundraising
feasibility study
• Project Kickoff:
Rowland Design
began programming
and schematic design
l March
2020: Rowland
Design
continued
schematic
design
l April 2020:
Rowland
Design
presented
schematic
designs
and color
renderings
December 2019
l May-July
2020: Pennington
& Company
concluded
fundraising
feasibility study