PROjECT TASKS COST
Renovate Second and Third Floor Sleeping Rooms $480,000
Renovate Second and Third Floor Bathrooms $150,000
Renovate First and Basement Common Areas $525,300
Renovate Kitchen, Replace Kitchen Equipment $120,000
Replace Roof per Seismic Requirement $80,000
Seismic Upgrades $140,280
PROjECT TASKS COST
Exterior Upgrades (walks, ramps, drainage, windows) $100,000
MEP, Sprinkler Upgrades $398,895
Soft Costs (design, engineering, permits) $199,448
Sales Tax $189,475
Contingency $238,340
BUDGET TOTAL $2,621,738