HIGHLIGHTS OF THE RENOVATION
RENOVATION COST ESTIMATES
Phase 1 (Basement and Ground Floor) $1,000,000
Phase 2 (2nd and 3rd Floors, Exterior) $1,250,000
Development Costs and Contingency $ 250,000
TOTAL PROJECT COSTS $2,500,000
Phase 2 (construction date: summer 2016)
Second Floor
• Expand front center of house to
accommodate two oversized
rooms
• Repurpose existing rooms at
front of house to provide
separate study and sleeping
areas
• Expand rear of house to provide
separate study and sleeping
areas
• Add second floor balcony at
rear
• Add study hall at south end of
building
• Update bathrooms
Third Floor
• Create lofts above all bedrooms
• Add study hall at south of
building
• Update bathrooms
Exterior
• Expand front entry and provide
new façade
• Fence in yard to allow for
outdoor living/gathering space
• Create enclosed covered
balcony