Phase I,
Summer 2015
• Waterproof foundation at front of
house
• Kitchen addition (385 sq. ft.)
• Southwest patio with basement
(900 sq. ft.)
• West deck with conditioned
storage area (115 sq. ft.)
• Kitchen renovation
• Dining room renovations (open up
to adjoining rooms)
• Weekend kitchen addition
• Guest bath with shower
• New door to deck (relocate
mechanical unit)
Phase II,
March through
December 2016
• Courtyard and east addition (three
stories over basement)
• Laundry/storage area renovation
• Convert rush storage to study area
• Hazardous waste abatement
• Roof replacement (new roof area
included in addition)
• New bathroom on north wing
• Convert bathroom to bedroom
Phase III,
January through
July 2017
• Officer's suite
• Reroute east corridor
• New hall toilets (replace finance
office/mail room)
• Guest bathroom (north wing)
• Bathroom expansion
• Update wiring in old addition
• Hazardous waste abatement