Our Project Plans
T
he Delta Xi Chapter alumnae
leadership has developed a solid
plan to address the long-term vi-
ability of the Tri Delta experience at Mizzou.
Through careful study, assessment, and plan-
ning, it has been determined that a renova-
tion and addition to our home are necessary
to meet the needs of today's students and
to remain competitive on campus. Working
with McAfee Construction of Columbia, the
Delta Xi House Corporation has developed a
tactical approach to our future.
The project highlights to the right and plans
outlined on the following pages are designed
to enhance the educational, personal, and
professional experiences offered by mem-
bership in Tri Delta.
PROJECT HIGHLIGHTS
PHASE 1 (Completed 2010-11)
D Fire-sprinkler/alarm system installation
PHASE 2 (Summer 2013-Fall 2013)
D Build addition on west side of home to relocate kitchen and dining to first floor
D Create commercial-size kitchen necessary for meals and events
D Expand dining room with 180 lecture/120 dining seating capacity—multi-use space
D Build new patio
D Create first floor bathroom with handicap accessibility along west wing
D Renovate house director's suite and president's room, including new bathrooms
D Create designated office space
D Relocate computer room to basement level
D Update and expand wireless technology
PHASE 3 (Complete Summer 2014)
D Demolish annex; use space for required parking
D Add bedrooms for 14 in new west wing addition (occupancy = 92 after renovation)
D Install new north parking lot (40+ spaces) and bike rack
D Make minor common area renovations
D Renovate second and third floor bathrooms
D Transform basement and lower level kitchen areas into library, study and craft spaces
D Build handicap accessible restroom
PROJECT COSTS
(Renovate 6,110 square feet, add 5,160 square feet)
Demolition, Renovation and New Construction $2,800,000
Furnishings and Appliances $130,000
Additional Costs $300,000
TOTAL $3,230,000