6 ILLINOIS CHAPTER
EXISTING
SITE PLAN
BUILDING-
CROSS SECTION
20 10 5 0
BUILDING CROSS SECTION
8/20/21 CHARLES D. BLECK, ARCHITECT
NEW CHANDELIERS TO
REPLICATE ORIGINAL
UNDER PIN EXISTING FOOTINGS
AND INCREASE CEILING HEIGHT
FROM 7'-6" TO 10'-0"
NEW STAIRS
NEW GRAVITY PERIMETER
UNDER DRAIN TIED INTO
CITY STORM SEWER
NEW STAIR TO MATCH THE
ORIGINAL GRAND STAIR CASE
UPDATE
EXISTING
STAIRS
UPDATE
EXISTING
STAIRS
GUT ENTIRE 2ND & 3RD FLRS. TO STUDS:
INSTALL HIGH PERFORMING INSUL'N.
ALL NEW CABINETS
NEW CEILING FANS
NEW ELEC. CIRCUITS &
RECEPTACLE TO MEET DEMAND
ALL NEW DOORS & FINISHES
AIR CONDITION ALL ROOMS
INSTALL HIGH SPEED WI-FI
NEW RECESSED LED LIGHTING
ORIGINAL
FLOOR LEVEL
PROPOSED NEW
BASEMENT FLOOR LEVEL
REFINISH WAINSCOT TO
REPLICATE ORIGINAL
NORTH
EXISTING SITE PLAN
0 5 10 20
DELTA UPSILON
FRATERNITY
HOUSE
REBUILD
BBQ
NEW DUMPSTER LOCATION
Total Project Cost: $4,000,000
CONSTRUCTION TIMELINE:
15 months (May to August 2021)