August: Projected
completion for fall
semester move-in
and recruitment
BUILDING FOR OUR NEXT GENERATION
5
A
lpha Omicron alumnae and undergraduate leadership have developed a solid plan to address the long-term viability and success of the Theta
experience at the University of Oklahoma. Through careful study, assessment, and planning, it has been determined that a renovation and expansion,
adding over 9,700 square feet, is necessary.
We must invest in our home to meet the needs of today's students.
ESTIMATED PROJECT COST: $11 MILLION
Project plans, renderings, and cost estimates are subject to change.
P R O P O S E D T I M E L I N E
2019 2020 2021 2022 2023 2024 2025
Project planning and
development
Alumnae communication
begins
Project planning paused
due to Pandemic
July-November:
Pre-campaign alumnae survey
and continued project planning
January-June 2024: Theta for a Lifetime
– The Campaign for 845 fundraising and
continued alumnae communication
July: Construction
begins