OUR PLAN
W
e know that major updates and long deferred maintenance to our Shelter are necessary, and that we
must invest now in our home to meet the needs of the next generation of students. The Beta Omicron
House Corporation and undergraduate leadership have developed the following plan to ensure our
long-term viability.
RENOVATION HIGHLIGHTS
PHASE 1
COMPLETED/PLANNED WORK
n Replace internal doors to meet fire code requirements
(completed)
n Convert presidential suite to advisor suite (spring 2021)
"Being a Delt and living in the Shelter taught me a lot about
life. Living with a lot of diverse personalities was a joy and a
challenge. We kept the Shelter operating like a small business;
I was able to apply the skills I learned from this to advance
my career. I want to ensure the same impactful experience is
available for future generations of brothers by investing in the
Shelter today." – Glenn Peterson '73
PHASE 2
FOUNDATIONAL WORK – ENERGY
EFFICIENCY, SHELTER LIVABILITY
AND CURB APPEAL
Expected to Begin Summer 2022
n Bathrooms $300,000
n Rec Room $683,000
n Lobby/Lounge Upgrades $279,000
n Envelope (Exterior) Upgrades $747,000
(including windows)
n Entry Canopy $18,000
n Mechanical System Upgrade $759,000
n Grease Trap/Sanitary Line Replacement $28,000
n Hot Water System Upgrade $73,000
Total $2,887,000
PHASE 3
ENHANCED LIVABILITY
Expected to Begin Summer 2025
n Bedroom Reconfiguration $890,000
n Remainder of Interior $294,000
n Chapter Room $40,000
Total $1,224,000
FUTURE PHASES
POTENTIAL ADDITIONAL PROJECTS
(Long Term – 10+ Years Out)
n Gym/Storage Addition $694,000
n Roof – Replacement/Photovoltaics $598,000
n Enhanced Accessibility (e.g., Elevator) $945,000